Sewer Department
The Village of Gowanda Sewer services were established in 1897 with the construction of sanitary sewers and a series of septic tanks through out the village. In 1959 the village added additional sewers and constructed a wastewater treatment plant on Aldrich Street in the Village. The Aldrich Street plant was updated in 1992 and a Bio solids composting facility was added in 1994 and updated in 2003.
Current Operations
Today this state of the art regional wastewater management facility services the Village of Gowanda, Village of Perrysburg, Collins Corrections, Gowanda Corrections and customers in the Towns of Collins and Persia.
The Village Wastewater Treatment plant is a state of the art 2.2 million gallon a day Biological Oxidation plant with phosphate removal and two stage
anaerobic digestion. The plant achieves 90% or greater removal
efficiency. All bio-solids produced by the plant are composted to produce class A compost suitable for distribution to the Public.
The Village of Gowanda Sewer Department is located on Aldrich Street in the Village. The department is staffed by 5 full time, 1 part time and 1 seasonal employees and has an annual budget of $647,890.
Facility Description
Design Flow
> 2.2 million gallons per day, 5 million gallon per day peak flow
> 30 miles of sanitary sewer
> Equilivent population server 10,000
> Current rate $1.80 per thousand gallons $12.00 minimum
> Average yearly charge $135.44
> 1,500 yards per year static pile Bio-Solids compost facility
> New York Department of Health Approved Environmental Laboratory
Staff
1 Chief operator, 2 operators, 2 maintenance laborers, 1 part time
operator, 1 1 seasonal summer employee.
|


|